Ok, so I looked around and found varying formulas for calculating the number of business days between two dates and all of them had shortcomings that made them unreliable so I went about making my own. Now I do borrow code from http://www.kodyaz.com/articles/sql-server-dates-table-using-tsql-cte-calendar-table.aspx to create my query. Here is the result:
DECLARE @TotalWorkingDays INT
DECLARE @StartDate DATETIME
DECLARE @EndDate DATETIME
DECLARE @CurrentDate DATETIME
...
SET DATEFIRST 7;
WITH CTE_DatesTable
AS
(
SELECT DATEPART (dw,@StartDate) as [dn], @StartDate AS [date]
UNION ALL
SELECT DATEPART (dw,DATEADD(dd, 1, [date])) as [dn], DATEADD(dd, 1, [date])
FROM CTE_DatesTable
WHERE DATEADD(dd, 1, [date]) <= @EndDate
)
SELECT @TotalWorkingDays = COUNT([dn]) FROM CTE_DatesTable WHERE [dn] NOT IN (7,1)
OPTION (MAXRECURSION 0);
SELECT @TotalWorkingDays
What happens with this query is that it counts the days between the start and end dates excluding Saturday and Sunday (7 and 1 using DATEPART with the dw argument).
Note: this query does NOT take in to consideration any holidays.